Lot Closure
Henderson Parking lot (Brown G) closes October 29, 2010
Contact JoLaine Teyssier (jat2@psu.edu) regarding parking reassignments.
Temporary Work Site Prepared
November 2010
Temporary work site prepared on south end of HUB Lawn for construction staging, material delivery, and temporary construction offices.
'Bridge' Closure
December 13, 2010
"Bridge" connecting Henderson Building and Henderson Building South abated and demolished.
Demolition
December 2010 - January 2011
Foundation
February 2011 - May 2011
Foundations for Biobehavioral Health Building completed.
Noise and vibrations will be heard and felt as the foundation is prepared.
Steel Structure
May 2011 - July 2011
Steel superstructure erected and completed.
Noise will be heard as steel is erected.
Utilities
May 2011 - August 2011
Site utilities installed.
Exterior
Exterior of building completed February 2012
Interior
February 2012 - November 2012
Interior fit-out of building.
Final Completion — Move-in
November 2012